The plant is operating at 100% power with no equipment out of service when an 86-2 LOR fault occurs on Bus NB02. The LOR initiates trips on the normal, alternate and diesel feeder breakers to the bus. EDG B starts and runs with its output breaker open. Assuming all Train A equipment functions as designed, which of the following actions should be performed?