The plant is at 100% power. GE RE-92, Main Condenser Vacuum Pump Vent Radiation Monitor, is showing increased activity.Chemistry has been notified and the leak has been quantified at 25 gpd. What action(s) are appropriate for this condition?
Explore more HVAC questions
Visit our
website
for other HVAC topics now!
Related questions
The Sullair compressor will trip on which of the following conditions?
Which of the following locations of the SGBS, is monitored by a process radiation monitor?
The plant is operating at 100% when a Steam Generator Tube Leak begins. GE RE-92, Condenser Air Removal Rad Monitor, reaches an Alert condition.RCS leak rate calculation indicates leakage increased by 0.4 gpm since it was last performed.What action is required?
What is the expected plant response to a loss of voltage to an NB bus?
The Emergency Diesel Engine lubricating oil sump level is maintained by which of the following?
The function of the Emergency Diesel Generator engine fuel supply accumulator is to ___________________________.
The caution prior to step 1 of EMG ES-03, SI TERMINATION, states manual action may be required if offsite power is lost after SI is reset.Why is this caution necessary?
The unit experiences a loss of off-site power, Diesel Generator "A" starts and loads onto NB01; Diesel Generator "B" fails to start.Which one of the Instrument/Service air compressors can be placed in service?
If directed to emergency start an EDG and the situation dictates the one must locally operate the main air start valve, where is the tool designed for this task located?
An Instrument/Service air compressor will automatically shutdown if it runs unloaded for how many minutes?
Assuming the Instrument Air System is operating normal per procedures, (i.e., Lead Unit Compressor supplying) and a loss of cooling water to the compressor occurs, the lead compressor will trip on:
Given the following conditions:* Reactor Power 100%* PZR Level 60% slowly increasing* PZR Pressure 2290 psig slowly increasing* Letdown Isolated* Charging 120 gpm and decreasing* S/G Levels 50% and stableWhat has occurred?
The Emergency Diesel Generator (EDG) is operating in parallel with its ESF bus when a Safety Injection Signal (SIS) is received. What is the Emergency Diesel Generator (EDG) response given these conditions?
The capacity of the Emergency Diesel Generator fuel oil storage tank is _________________ for each diesel. The Technical Specification capacity of 85,300 gallons will ensure sufficient fuel for a minimum of ___________ run time at the EDG rated output.
The Control Building Air Supply process radiation monitor GK RE-04 (gaseous channel) alarmed HiHi causing a CRVIS actuation.Which action would be expected to occur as a result of this actuation?
The purpose of the CWSH standby control panel 1PL14J is to:
A 5 second time delay is provided between breaker closures on both the LOCA and Shutdown Sequencer actuation.Which of the following describes the purpose of this delay?
Select which Emergency Diesel Generator (NE) subsystem removes heat from:* Cylinder Walls* Governor Oil Cooler* Turbo-Charger bearing oil cooler A. Jacket Water Cooling SystemB. Intake AirC. Intercooler SystemD. Lube Oil System
The Fuel Oil accumulator ___________________ for the Emergency Diesel Engine.